The inspection request phone number is (760) 435-3925. You must leave your request on this recorder by 3:30 pm on a business day to get the next-business-day inspection.
Please see the handout on Applicable Codes & Regulations.
For inspections within the home, the homeowner or permit holder must be present to allow for access into the home. For outdoor projects such as pools, patio covers, solar installations and reroofing, we will perform the inspection without the home owner being present if a note is left for the inspector granting access. In both cases, the plans and permit must be accessible to the inspector or no inspection will be performed. A proper ladder must be provided for roof level inspections.
In order to check the status of your plans, please have the job address and/or the plan ID number, and call the main office at (760) 435-3950. You can also check the status on eTRAKiT, the online permitting system.
New residential submittals usually take 7-21 calendar days, new commercial buildings usually take 21 calendar days, and tenant improvement submittals take approximately 14 calendar days. Although the Building Division does its best to adhere to these target dates, the time frames do vary according to the volume of plan submittals at that time.
The only way to be sure is to turn in the Permit Exemption form. It involves drawing a plot plan and routing that plan to various departments for approval. Please see our Permit Exemption Policy.
Please see the State of California, Housing and Community Development Web site at: http://www.hcd.ca.gov/building-standards/permits-inspections.shtml and go to section 1018(c) for a list of work that is exempt from a building permit.
According to the County Assessor, whether or not your taxes will increase depends on various factors, not just the fact that you obtained a permit.
Yes, the building code does not exempt window replacements; therefore, a permit is required. The Building Division will ensure the windows meet current Energy regulations and emergency egress requirements, among other code issues. If the windows are just being retrofit within the same opening and the weather seal is not being broken, then a permit may not be required. Please see the Window Replacement Submittal Requirements and Policy.
Yes, the spa is required to be permitted, inspected, listed, labeled provided with a code compliant electrical circuit. The spa is also required to have fencing and/or some other safety device, such as an approved safety cover.
Yes, a permit is required and it is important to contact San Diego Gas & Electric. The panel needs to be disconnected by SDG&E before the work is done. Once the work is finished, a Building Inspector will inspect the work and if the inspection passes, the Building Division will contact SDG&E to release the utilities. SDG&E will then reconnect the utilities.
Yes, a building permit is required for all types of demolition work. Please refer to the Minimum Submittal Requirements for Demolish Permits handout.
A building permit will expire if the work has not been completed within three years of the issuance date. One extension of six months may be requested, in writing to the Chief Building Official, prior to the expiration of a permit. Additional fees may apply.
Construction work covered by a building permit is allowed Monday through Friday, 7:00 am to 7:00 pm. Work is also allowed to be performed by the owner of a property on Sundays 9:00 am to 5:00 pm. Construction work is not permitted on nationally recognized holidays.
Construction work covered by a building permit is allowed Monday through Saturday, 7:00 am to 7:00 pm. Work is also allowed to be performed by the owner of a property on Sundays 9:00 am to 5:00 pm. Construction work is not permitted on nationally recognized holidays.