I’d like to build a room addition on my property, and I want to know if it’s even possible. Where do I start?

You’ll want to start by visiting the Planning Division, which regulates what you can build on your lot per the Zoning Ordinance. They have information regarding the maximum lot coverage percentage, minimum setback requirements (distance from property lines to structures), parking requirements and maximum height limitations for your lot. Once you find out what your parameters are, you can begin designing your room addition. The Building Division reviews plans to make sure your design meets minimum Building Codes; this process takes 10 to 20 working days for the first plan check and 10 working days for subsequent checks. The Building Dept has some helpful handouts to help you submit a complete set of plans. Once your plans have been approved, the building permit will be issued and you can start building.