Facility Improvements included a new restroom facility and drinking fountain.
Project Manager: Kymberly Corbin, (760) 435-3534 or KCorbin@oceansideca.org
Project #: CIP21-00017
Program: Parks
Completion: Summer 2022
Additional courts at Melba Bishop Park.
Project Manager: Kymberly Corbin, (760) 435-3534 or kcorbin@oceansideca.org
Project #: CIP21-00009
Program: Parks
Completion: Summer 2022
Sports Field lighting was added to the other half of Mance Buchanan park.
Project Manager: Kymberly Corbin, (760) 435-3534, kcorbin@oceansideca.org
Project #: CIP21-00013
Program: Parks
Completion: Summer 2022
Project improved the fire training facility located on Jones Road with a burn structure, pump house, and deflection wall constructed within the existing site limits. This project was funded in part by Measure X.
Project Manager: Kymberly Corbin, (760) 435-3534 or kcorbin@oceansideca.org
Program: Municipal Buildings
Completion: Summer 2022
Please visit the El Corazon Aquatic Center page for more details and updates.
Development of a new aquatics center adjacent to the El Corazon Senior Center. The project included administration, locker-room and equipment facility buildings, a new shared multi-purpose hall, a 56-meter competition pool, educational pool, splash pad and outdoor event areas.
Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org
Project #: CIP15-00020
Program: Municipal Buildings
Completion: August 2021
Please visit the Quiet Zone Update page for more details and updates.
Construction of safety-related improvements at the five at-grade railroad crossings in the coastal rail trail corridor. The specific crossings are Surfrider Avenue, Mission Avenue, Wisconsin Street, Oceanside Blvd, and Cassidy Street.
Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org
Project #: CIP14-00013
Program: Transnet
Completion:
New Traffic Signal improvement located at RDO & San Ramon.
Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org
Project #: CIP19-00006
Program: Thoroughfare-Signals
Completion: March 2021
Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org
Project #: CIP20-00009
Program: Transnet
Completion:
This project includes the demolition and reconstruction of the Tyson Street Park restroom building.
Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org
Project#: CIP17-00003
Program: Parks
Duration: 03/14/2017 - 01/09/2020
![]() |
![]() |
Road Repairs: potholes/slurry seals.
Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org
Project #: CIP19-00014
Program: SB-1
Duration: Began October 2019, with completion of March 2021
FY19-20 - Slurry Seal Project Location Map
|
![]() |
This project provides asphalt overlay of City streets. This project is funded in part by Measure X.
Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org
Project #: CIP19-00013
Program: SB-1
Duration: Began October 2019, with completion of November 2021
Road Repairs: potholes/slurry seals.
Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org
Project #: CIP21-00002
Program: SB-1, Trans Net, Measure X
Duration: Began September 2021, with completion of November 2021
The project provides asphalt overlay of City streets. Street selections are made based on computerized pavement management system information, staff's review to determine the high priorities for restoration, and citizen's reports of deteriorating street conditions. This project is funded in part by Measure X.
Full Depth Reclamation (FDR) Process:
https://www.youtube.com/watch?v=c-oMzqB0MS0
https://www.youtube.com/watch?v=mWtDOB5n7tI
Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org
Project #: CIP21-00003
Program: SB-1, Trans Net, Measure X
Duration: Began September 2021, with completion of November 2021.
This project includes the construction of median frontage improvements on the south side of Mission Avenue.
Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org
Project#: CIP16-00009
Program: Transnet
Duration: 08/19/2016 - 06/04/2020
![]() |
This project includes the construction of new park improvements.
Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org
Project#: CIP18-00005
Program: Parks
Duration: 05/08/2018 - 12/03/2020
![]() |
This project includes the rehabilitation and remodel of Fire Station 4.
Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org
Project#: CIP18-00002
Program: Municipal Buildings
Duration: 02/27/2018 - 03/24/2020
| |
![]() |
|
This project includes the construction of new median and pedestrian barriers at the intersection of College and North River Road.
Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@Oceansideca.org
Project#: CIP18-00001
Program: N/A
Duration: 02/13/2018 - 06/04/2020
| |
|
Drainage improvements for Casa De Amparo and Ivey Ranch.
Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@Oceansideca.org
Project#: CIP18-00006
Program: Drainage
Duration: 05/31/2018 - 06/04/2020
Installation of emergency backup power to City of Oceanside Guajome Conference Room.
Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@Oceansideca.org
Project#: CIP18-00014
Program: Municipal Buildings
Duration: 10/30/2018 - 06/04/2020
Installation of emergency backup power to OPD and Mission Library.
Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@Oceansideca.org
Project#: CIP18-00019
Program: Municipal Buildings
Duration: 10/30/2018 - 06/04/2020
Installation of fiber optic conduit for reverse osmosis plant to improve communication capabilities.
Project Manager: Victor Velasco, (760) 435-5102
Project#: CIP18-00023
Program: Miscellaneous City Capital
Duration: 11/28/2018 - 06/04/2020
This project includes ADA improvements at the harbor tunnel pedestrian crosswalk.
Project Manager: Victor Velasco, (760) 435-5102
Project#: CIP19-00005
Program: Harbor
Duration: 03/15/2019 - 11/23/2020